SPMTs transport fully rigged heavy lifter

Premium Content

26 January 2009

SPMTs transport the fully rigged Mammoet PTC-DS ring crane at a power station in Neurath, Germany

SPMTs transport the fully rigged Mammoet PTC-DS ring crane at a power station in Neurath, Germany

Mammoet was awarded the contract to supply a PTC-DS (double stacked) super heavy lift crane to build one of the largest power stations in Europe, located in Neurath, Germany.

The new brown coal-fired power plant consists of two identical power units of 1,100 MW each.

Due to the height of the power plant, the PTC-DS had to be modified with a 134.6 m main boom and an additional 69.3m jib, totaling 203.9 m. Basic maximum capacity of the PTC-DS is 1,600 tonnes, with a load moment of 33,705 tonne-metres. The crane and boom reached a tip height of 207.7 m.

"With that it even dwarfed the famous 157 m high Kölner Dom [Cathedral] in nearby Cologne [Köln]," says the company.

A challenge was the relocation of the fully rigged PTC-DS from Block F to Block G. Following an emergency situation at the power plant during its construction, the work was re-scheduled and the crane was returned to its original location at Block F, which was in a later stage of construction.

Mammoet's ring-based cranes are designed to be relocated using purpose built self-propelled modular transporters or SPMTs. In this case 100 axle lines were positioned underneath the ring of the crane for its relocation. Total transport weight of the PTC-DS crane, excluding the SPMTs, was 2,080 tonnes.

Smart lifting: How to balance cost and safety
Rental experts discuss equipment strategies for today’s complex lifting challenges
How microgrids are powering the data center boom
As the global demand for data grows, businesses are looking beyond the grid for uninterrupted operation
Demolition & Recycling International October-December 2025
Demolition & Recycling International November-December 2025