Transformer project for Steder Group

Premium Content

26 August 2015

A total of six transformers were moved during the project

A total of six transformers were moved during the project

Transport company Steder Group Djibouti has completed the transport of six transformers in Ethiopia.

Four of the transformers weighed 98 tonnes and the remaining two weighed 117 tonnes and measured 5.2 metres tall. The transformers were transported from Djibouti port to Gebre Guracho and Chancho in Ethiopa. The route was 1,050 km.

Due to the height of the cargo, the convoy had to use several bypass roads and electricity cables had to be lifted along the way. The rainy weather also created some problems, causing the gravel roads to become flooded and slippery. On certain occasions, graders and or dozers had to be used so the convoy could pass, a spokesperson said.

Despite the difficult conditions, all six transformers were delivered to site. Steder Group Dijbouti is a member of the Worldwide Project Consortium (WWPC) and is Cargo Equipment Experts (CEE) member for Djibouti.

Will fuel-agnostic engines power the next era of construction?
Flexible engine platforms are emerging as a way to balance performance, flexibility and future regulatory demands
Beyond torque: The challenge of power management for crushing equipment
How OEMs and operators are managing to maximise uptime for equipment that has to pass the ultimate stress test on a daily basis
Crawler-mounted boom lifts rise to the challenge of bridge work
From remote creek beds to inner city overpasses, crawler-mounted boom lifts are proving indispensable for bridge construction, inspection and maintenance