WINNER ENTRY 9 Turbine tale

11 April 2008

The 128 tonne top section is lifted onto the turbine mast

The 128 tonne top section is lifted onto the turbine mast

The project was to install two 5 MW wind turbine generators in 40 m deep water, 23 km off the North East coast of Scotland as part of a European Distant Offshore Wind Farms With No Visual Impact (DOWNVInD) project to establish the viability of large capacity wind turbine farms in deepwater and offshore locations.

Weldex was contracted to complete the onshore assembly and the first phase of the installation at Nigg. The company erected a support base in two sections, each weighing 125 tonnes. A 61 m, 230 tonne tower section was installed on the frame and the turbine components, totalling 734 tonnes. Once at the Beatrice Wind Farm site, a Weldex crane mounted on the Rambiz, a 3,300 tonne barge mounted crane operated by marine contractor Scaldis, assisted in the piling work to anchor the substructure in the seabed.

Latest News
Powering up: how batteries are making tower cranes greener
Hong Kong-based battery manufacturer Ampd Energy is expanding globally on a promise of providing a viable alternative to diesel generators for powering tower cranes
Manitex expands PM crane sales network in USA
First Fleet Truck Sales to offer PM cranes and Manitex aerial work platforms in Florida
Heading to America: Tadano’s 100 ton all electric EVOLT RT
The Tadano EVOLT is the first electric rough terrain crane designed to work in North America