WINNER ENTRY 9 Turbine tale

Premium Content

11 April 2008

The 128 tonne top section is lifted onto the turbine mast

The 128 tonne top section is lifted onto the turbine mast

The project was to install two 5 MW wind turbine generators in 40 m deep water, 23 km off the North East coast of Scotland as part of a European Distant Offshore Wind Farms With No Visual Impact (DOWNVInD) project to establish the viability of large capacity wind turbine farms in deepwater and offshore locations.

Weldex was contracted to complete the onshore assembly and the first phase of the installation at Nigg. The company erected a support base in two sections, each weighing 125 tonnes. A 61 m, 230 tonne tower section was installed on the frame and the turbine components, totalling 734 tonnes. Once at the Beatrice Wind Farm site, a Weldex crane mounted on the Rambiz, a 3,300 tonne barge mounted crane operated by marine contractor Scaldis, assisted in the piling work to anchor the substructure in the seabed.

Truckstop.com and ProMiles partner up to streamline heavy haul quoting
Truckstop.com and ProMiles have expanded the Heavy Haul Load Board with route-based quoting for oversize and overweight freight.
SCRA issues statement on tariff ruling by Supreme Court
Industry association comments on US ruling overturning import tariffs
Mi-Jack acquires new facility in Illinois, USA
New 200,000 square-foot production facility to meet critical capacity needs