Kahl Schwerlast relocates gantry crane

30 July 2014

Goldhofer PST heavy-duty modules were used to rotate and reposition Duisburg Harbour’s 630 tonne por

Goldhofer PST heavy-duty modules were used to rotate and reposition Duisburg Harbour’s 630 tonne portal crane

A 630 tonne dockside gantry crane was relocated as part of Duisburg Harbour's upgrade in Duisburg, Germany.

The upgrade will increase the harbour's container handling capacity from 1 million standard containers to five million, a spokesperson said. To help achieve this, four additional container cranes, an extra 13 hectares of shipment and storage area, and the relocation of the gantry crane, is to be carried out.

Kahl Schwerlast, main contractor for the project, moved the 630 tonne Trimodal gantry crane from its original location parallel to the quayside to Logport 1 using two six-axle and two four-axle self-propelled transport modules from the Goldhofer PST/SL-E series.

The self propelled modules have hydrostatic drive, electronic multi-way steering and a payload of 45 tonnes per axle line. To increase the payload, the two four-axle modules were combined with three-axle THP heavy-duty modules, a spokesperson added. Power was supplied by four power packs with an output of 155 kW (210 PS) and 360 kW (490 PS).

The crane was 139 metres long, 20 m wide and 18 m high. It was turned 90 degrees to create a waterside outreach of a 15 m, a spokesperson said. Tim Kruse, who helped manage the project, said, “That was a special challenge for us. Manoeuvring a crane of that size in such a tight space with almost centimetre precision is a tall order.

“Manoeuvring so close to the quayside is always a little bit dangerous. So the six additional THP axles provided a margin of safety that permitted us to slightly reduce the axle load on the individual PST modules.”

To relocate the gantry, the crane was raised 300 mm and rotated 90 degrees using the modules, before being repositioned on girders. Once in place, eight heavy-duty cranes were used to lift the portal crane into its final position. The harbour was closed during the process.

“With the Goldhofer PST modules, we are perfectly equipped to handle really heavy outsized loads with almost centimetre precision,” Kruse added.

Latest News
Platform Basket delivers first 54m spider
The innovative 54T spider goes to Minoege
Andy Wright joins UK power specialist
Former Sunbelt UK CEO appointed executive chair
Stantec acquires UK-based engineering design rival Hydrock
Canadian engineering firm Stantec has bought its UK-based engineering design rival Hydrock, in a move that it said would strengthen its UK offering.